Approval flow
Source-backed from LMC eBPS permit process, required document page, and published building permit charge schedule.
Prepare drawings and owner file
Prepare signed architectural/structural drawings, land records, tax receipts, designer licence copy, and any consent or access-road papers before submission.
Submit to LMC eBPS / permit desk
LMC receives the permit application inside eBPS and checks it against building by-laws and applicable NBC references.
Ward and technical review
The file moves through ward/local verification and technical review. Boundary points should be clear before field inspection.
Plinth-level inspection
LMC's document page states the process is handled at plinth-level inspection and then the stage above plinth up to roof.
Above-plinth permit and completion
After approved-stage construction, apply for completion certificate. Final checks compare built work with approved drawings before service connections and completion records.