Approval flow
Source-backed from Kathmandu Metropolitan City eBPS building permit process, document list, fee schedule, and completion certificate flow. The live KMC eBPS references page also lists the 2083 amendment reference and Online Approval Format 2026; verify the active municipal reference set before filing.
- Day 1
Submit electronic application
Submit drawings to the metropolitan city with the land title certificate and owner/company identity through the eBPS workflow.
- Day 2
File moves to ward office
The municipality forwards the file to the ward office where the land is located for local verification.
- Day 4
Ward field check and neighbour notice
Ward staff check the site and send notice to neighbouring landholders.
- Day 8-23
Notice maturation and local inquiry
The notice period matures, then the ward conducts local inquiry or sarjmin before returning the file.
- Day 27-29
Municipal approval stage
The ward sends the file back and KMC starts issuing the construction permit certificate and approved drawings. At least one neighbour consent is expected; otherwise the owner may need a commitment letter for future disputes.